Builder Process for Stand-Alone Electrical Services

You are welcome to ask questions and upload documentation using the contact form at the bottom of this page. All Submissions go to MyRequest@StradaElectric.com.

Download The Information


This script should be pla

3 Ways To Connect With Strada Today

Process Overview

Builder emails request for new electrical services

  • Service Writer emails builder form or it can be downloaded online
  • Form must be completed and emailed to myrequest@stradaelectric.com

Pre-Site visit requirements

  • Electric utilities in ground or transformer locations staked
  • For pond aerators: Must be set or cabling staked at edge of pond

White flagged, locates called in by Strada Electric, Security & Air Conditioning

Service Writer emails proposal to be reviewed & signed.

  • Estimated turnaround time to receive proposal after receiving builder form is 3-5 business days

Apply for permit (permitting form, signed contract, riser/plans if needed)

  • Estimated permit turnaround time is 5-10 business days

NOC if it’s over 2500 (we need the ORIGINAL copy returned to us via FedEx); Inspections will not be scheduled until original copy is received, and we can record the document.

When permit is issued it will be emailed to service team and builder to begin scheduling process

Release all materials, address labels and available fault current labels required after permit is issued

  • After permit is issued, we have 5-7 business days to start work

Utilities need to be in the ground or staked

Pole mounted irrigation controllers & fountain controllers sent to us or be on site prior to install

We can start to schedule Underground inspections 1-3 business days after work has been started depending on length of trench. Typical 60-100A irrigation control services duration time is 1-3 business days from start until final inspection

Schedule utility transformer opening to install service conduit and conductors. 3 Business days to complete.

Approved final inspection results along with image of blue sticker “Orange County” will be emailed to builder to schedule power release/ Meter set with utility company provider